Google search engine

The Electricity Company of Ghana (ECG) has started the installation of two high-capacity power transformers at the Ridge Bulk Supply Point in Kumasi, a major step to reinforce supply reliability across the metropolis. 

‎The project replaces two existing 20/26MVA transformers with upgraded 30/39MVA units, significantly boosting station capacity and easing pressure on the network.

‎This upgrade directly addresses recent intermittent outages and voltage fluctuations in parts of Kumasi, which have been driven by rising demand rather than generation shortfalls.

‎ECG’s Acting Managing Director has emphasized the strategic importance of the project:

‎“Kumasi is expanding, and electricity demand is rising with it. This upgrade ensures our infrastructure keeps pace so customers can enjoy more stable and reliable power.”

‎On site, Manager, Substation & Switchgear Maintenance for Ashanti Sub-Transmission described the work as both urgent and complex: “The existing transformers are under pressure. These new units give the system breathing room and improve overall stability.”

Teams from Accra and Ashantii Sub-Transmission Divisions are jointly coordinating the installation. The transformers are scheduled to be installed by May 6 and 7, 2026, with energization planned shortly after.

‎Installation schedule:

  • May 6: Replace and energize Transformer 2
  • May 7: Replace and energize Transformer 1

Outage details
‎To ensure smooth safety operations, ECG will implement controlled outages:
‎- Dates: May 6 and May 7
‎- Time: 9:00 AM – 3:00 PM
‎There will be temporary shutdown of sections of the 33kV network and managed load distribution on 11kV feeders.

‎ECG assures customers that the interruptions are carefully planned and limited in duration.

‎”We understand the inconvenience, but these are necessary steps to deliver a more reliable system,” added Collins Manu, Communications Officer of Ashanti Sub-Transmission.

By Benjamin Aidoo