The road section linking the Obetsebi Lamptey Interchange to the Metro Mass area at Pamprom Junction is expected to reopen to motorists between December 15 and 20, 2026, as work on the first phase of the drainage improvement project nears completion.

Project Manager of the Greater Accra Resilient and Integrated Development (GARID) Project, Cephas Ofori, said about 90 per cent of the first phase had been completed, with contrac tors working to meet the mid-December reopening target.

He said the remaining activities included backfilling and restoring the road pavement to allow motorists to use the stretch again.

Speaking on Channel One News, November 21, Ofori said the planned reopening was intended to ease traffic congestion around the interchange, particularly during the Christmas period.

“We are targeting around the 15th to 20th of December. That is when we are opening the road to the motoring public, from Obetsebi Lamptey through to the Metro Mass area, which we call the Pamprom Crossing,” he said.

According to him, major construction activities, including demolition, excavation, the construction of base walls and installation of cover slabs, have been completed.

He added that work on the second phase, covering the stretch from Pamprom Crossing to First Light, had also commenced.

The westbound carriageway of the Dr Busia Highway from Pamprom Junction was closed on September 7 to facilitate the drainage works under the GARID Project. The first phase of the closure was initially expected to be completed in November.

Meanwhile, GARID Project Communications Specialist Philip Dunyo said public education and the provision of alternative routes had helped manage traffic during the construction period.

He said motorists had generally complied with the traffic management arrangements introduced ahead of and after the closure, helping to prevent major gridlock and maintain traffic flow around the area.